Who does what, and where the app stops you. From Lesson 2; every rule checked in the app on 2026-10-15.

StepWhoWhereThe app refuses if…
Raise → createdSite, plant, adminWork Order Center → + Log Corrective / PM Work Order; or Quick Actions → New WOyou are corporate
Approve (1 to 3 levels) → approvedL1 plant · L2 corporate · L3 adminApprove on the row; corporate: Work Order Approvalsyou raised it
Assign → assignedPlant, adminAssign on the row, or Dispatchnot fully approved (emergencies included)
Safety packTechnician submits JHA; plant approves JHA, mitigates risk; supervisor records toolbox talk; permit and LOTO when requiredHSE Center (JHA, toolbox), Safety Permits(nothing starts until it is done)
Start → in progressAssigned technicianStart Work → Pre-Start Safety Verificationany red pack item, or the 4 confirmations not ticked
Complete → completedAssigned technicianAnswer every Checklist step, then Complete → 4 statements + notes (+ downtime hours on corrective work)a checklist step blank, a statement not ticked, no downtime on corrective work
Verify → verifiedPlant level, not the doerVerify (failure, cause and remedy codes for corrective work); e-signedyou are site level, you did the work, or codes are missing
Close → closedPlant levelClose; e-signedit is not verified

Approval levels

How many: the job's value sets it (standard bands: under $5,000 one level, from $5,000 two, from $50,000 three; no estimate = hours × $50), and priority can only raise it: high at least 2, critical and emergency always 3. No band set up at all means 3.

Deadlines

Critical 4 h · High 1 day · Medium 3 days · Low 7 days, from the moment it is raised. Changing priority changes the deadline.

Off the ladder

On hold: plant level, from any live step. Cancelled: plant level or admin, with a reason.