Using Voltara Intelligence · Reference
Work order card
Who does what, and where the app stops you. From Lesson 2; every rule checked in the app on 2026-10-15.
| Step | Who | Where | The app refuses if… |
|---|---|---|---|
| Raise → created | Site, plant, admin | Work Order Center → + Log Corrective / PM Work Order; or Quick Actions → New WO | you are corporate |
| Approve (1 to 3 levels) → approved | L1 plant · L2 corporate · L3 admin | Approve on the row; corporate: Work Order Approvals | you raised it |
| Assign → assigned | Plant, admin | Assign on the row, or Dispatch | not fully approved (emergencies included) |
| Safety pack | Technician submits JHA; plant approves JHA, mitigates risk; supervisor records toolbox talk; permit and LOTO when required | HSE Center (JHA, toolbox), Safety Permits | (nothing starts until it is done) |
| Start → in progress | Assigned technician | Start Work → Pre-Start Safety Verification | any red pack item, or the 4 confirmations not ticked |
| Complete → completed | Assigned technician | Answer every Checklist step, then Complete → 4 statements + notes (+ downtime hours on corrective work) | a checklist step blank, a statement not ticked, no downtime on corrective work |
| Verify → verified | Plant level, not the doer | Verify (failure, cause and remedy codes for corrective work); e-signed | you are site level, you did the work, or codes are missing |
| Close → closed | Plant level | Close; e-signed | it is not verified |
Approval levels
How many: the job's value sets it (standard bands: under $5,000 one level, from $5,000 two, from $50,000 three; no estimate = hours × $50), and priority can only raise it: high at least 2, critical and emergency always 3. No band set up at all means 3.
Deadlines
Critical 4 h · High 1 day · Medium 3 days · Low 7 days, from the moment it is raised. Changing priority changes the deadline.
Off the ladder
On hold: plant level, from any live step. Cancelled: plant level or admin, with a reason.
Stuck?
- “Approved but still created”: waiting for the next level.
- Start Work is grey: open it and read the red items.
- Open Timeline on the row to see every step, with who and when.